The Water Orton viaducts taking shape. The construction of one of the most complicated parts of the HS2 project took a step forward over the Christmas break, with the completion o ...
With HS2 soon to undergo a fundamental reset, it has assessed its achievements in 2025.
HS2 has confirmed that its aim to get trains running between Birmingham and London between 2029 and 2033 "cannot be achieved" ...
HS2 has confirmed that its aim to get trains running between Birmingham and London between 2029 and 2033 "cannot be achieved" ...
In its end-of-year update, HS2 said “significant progress” had been made during 2025, adding that the scheme is now at an ...
The construction of one of the most complicated parts of the HS2 project took a step forward over the Christmas break, with the completion of two key viaduct spans over the existing ...
HS2 chief executive officer Mark Wild visits the Old Oak Common station box site (Jonathan Brady/PA) The cost of building HS2 could hit £66 billion, according to a progress report published by the ...
HS2 has today (Monday December 29) published figures to show “significant headway” being made on the construction of the high ...
The cost of building HS2 could hit £66 billion, according to a progress report published by the Department for Transport. HS2 Ltd estimated the cost of the high-speed rail project would be £54 to £66 ...
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The ...